Kiara Advani, Sidharth Malhotra embrace parenthood for the second time‘Sometimes we get addicted to our own greatness’: Manoj BajpayeeDulquer Salmaan’s ‘Aakasamlo Oka Tara’ gets November 20 release date‘Mirzapur: The Movie’ crosses Rs 100 crore at domestic box office in opening weekendAmitabh Bachchan admits difficulty decoding Gen Z slangWatch: Nagarjuna releases trailer of Allari Naresh-starrer ‘Ramba Oorvasi Menaka’“Tum bahut lambe ho…”: Big B shares struggles of early acting daysNayanthara reveals how Geethu Mohandas convinced her to join ‘Toxic’Sonu Nigam says childhood anger fuelled his passion and shaped his singing careerYash takes out extra time time to pose for selfies with fans before leaving Mumbai airport

Hyderabad set to get metro by December

Posted March 23rd, 2017, 10:34 AM IST

Hyderabad set to get metro by December

Hyderabad: The state government on Wednesday informed the Legislative Assembly that Hyderabad Metro Rail operations will commence by this year-end.

Municipal minister K T Rama Rao told the house that the Miyapur-LB Nagar and Nagole-Hitech City stretches of 27-km each will be launched in the first phase by 2017-end.

“These two stretches of 54 km will be ready for commercial operations by this year-end. The two stretches form an important component of the 72-km Metro Rail project. Hyderabadis can avail Metro Rail services by this year-end,” Mr Rao announced.

The government had claimed earlier that Metro Rail operations would begin on June 2, 2017, on the third anniversary of the formation of Telangana state.
Metro Rail deadlines have been missed continuously since 2014 due to various reasons such as realignment issues and delay in acquisition of properties.

HMR officials say that the Nagole-Mettuguda and SR Nagar-Miyapur stretches were completed and ready for operations in mid-2016, but the government wants these stretches to be extended to LB Nagar and Hitech City and hence the delay.

“All the necessary clearances to operate trains from SR Nagar to Miyapur and Nagole to Mettuguda have already been obtained. All the stations are ready. But the government wants extension of these stretches, which will be completed by September,” said an official.