500 mw unit of Vallur plant begins generation
Posted February 26th, 2015, 11:18 AM IST

Chennai: The third 500 MW unit of the Vallur thermal power plant will commence commercial operation from Wednesday midnight to provide much needed relief to the state. The state will get about 358 mw as its share from the unit and it will help Tangedco to meet the growing power demand during the ensuing summer months. According to sources in National Thermal Power Corporation (NTPC), the unit III will be starting commercial operation from February 26.
The third unit has completed the mandatory 72 hours continuous full capacity operation between December 7 and 10 for achieving commercial operation declaration. However, the declaration of commercial operation was delayed due to breakdown of a coal conveyor and commissioning of the additional coal grab system in the Ennore port to unload coal from the ships. The three units of Vallur, which is a joint venture of the NTPC and Tangedco, together will supply 1074 MW out of its total capacity of 1,500 MW. The first and second unit is already under commercial operation since November 2012 and August 2013.
After obtaining the mandatory environmental clearance for the project, the first unit of the 2X500 MW NLC Tamil Nadu Power Limited (NTPL), a joint venture of the Tangedco and the NLC, has been test synchronised with the grid on February 18. “We successfully test synchronized the unit on February 18 and we operated the plant for an hour. It went on well. Since we synchronized the unit with oil, we are planning to go for coal firing synchronization on first week of March.
Once it is done, the unit will start supplying infirm power to the grid,” a senior official of NTPL told DC.The official added that the works are on to subsequently synchronise the unit II to the grid. “We are hopeful of synchronising the second unit by March end or in April,” the official said.
The third unit has completed the mandatory 72 hours continuous full capacity operation between December 7 and 10 for achieving commercial operation declaration. However, the declaration of commercial operation was delayed due to breakdown of a coal conveyor and commissioning of the additional coal grab system in the Ennore port to unload coal from the ships. The three units of Vallur, which is a joint venture of the NTPC and Tangedco, together will supply 1074 MW out of its total capacity of 1,500 MW. The first and second unit is already under commercial operation since November 2012 and August 2013.
After obtaining the mandatory environmental clearance for the project, the first unit of the 2X500 MW NLC Tamil Nadu Power Limited (NTPL), a joint venture of the Tangedco and the NLC, has been test synchronised with the grid on February 18. “We successfully test synchronized the unit on February 18 and we operated the plant for an hour. It went on well. Since we synchronized the unit with oil, we are planning to go for coal firing synchronization on first week of March.
Once it is done, the unit will start supplying infirm power to the grid,” a senior official of NTPL told DC.The official added that the works are on to subsequently synchronise the unit II to the grid. “We are hopeful of synchronising the second unit by March end or in April,” the official said.
- Kiara Advani, Sidharth Malhotra embrace parenthood for the second time
- Amitabh Bachchan admits difficulty decoding Gen Z slang
- Yash takes out extra time time to pose for selfies with fans before leaving Mumbai airport
- Bollywood stars shower blessings on Anshula Kapoor Rohan Thakkar at wedding reception
- Shilpa Shirodkar recalls losing Chaiya Chaiya with SRK
- Watch Russian couple dramatic proposal atop Empire State Building sparks global buzz
- Aamir Khan says his wedding with partner Gauri Spratt will be intimate affair with family and friends
- Actress Sreeleela recalls balancing MBBS medical exams with Viral Vayyari song shoot on Doctors Day
- US removes four Indian firms from sanctions list
- Suriya joins hands with T J Gnanavel for new hombale films project
- US Iran agree to sustain Strait of Hormuz ceasefire resume broader nuclear talks
- Telangana Governor CM Revanth Reddy urge people to join fight against drug abuse
- Samantha Confirms Pregnancy Shares Maternity Leave Plans Have To Take A Small Break
- Allu Arjun to appear in court on Monday in Sandhya Theatre stampede case
- Yoga centres to be set up in all villages announces CM Chandrababu Naidu
More News
Photos
Latest
- Kiara Advani, Sidharth Malhotra embrace parenthood for the second time
- ‘Sometimes we get addicted to our own greatness’: Manoj Bajpayee
- Dulquer Salmaan’s ‘Aakasamlo Oka Tara’ gets November 20 release date
- ‘Mirzapur: The Movie’ crosses Rs 100 crore at domestic box office in opening weekend
- Amitabh Bachchan admits difficulty decoding Gen Z slang
- Watch: Nagarjuna releases trailer of Allari Naresh-starrer ‘Ramba Oorvasi Menaka’
- “Tum bahut lambe ho…”: Big B shares struggles of early acting days
- Nayanthara reveals how Geethu Mohandas convinced her to join ‘Toxic’
- Sonu Nigam says childhood anger fuelled his passion and shaped his singing career
- Yash takes out extra time time to pose for selfies with fans before leaving Mumbai airport
A PHP Error was encountered
Severity: Warning
Message: file_get_contents(http://www.indiaaffiliates.in/ads.php?size=300X250): failed to open stream: Connection refused
Filename: views/newsdetails.php
Line Number: 57
Backtrace:
File: /home/sites/43a/5/599366ad77/public_html/application/views/newsdetails.php
Line: 57
Function: file_get_contents
File: /home/sites/43a/5/599366ad77/public_html/application/controllers/News.php
Line: 135
Function: view
File: /home/sites/43a/5/599366ad77/public_html/application/controllers/News.php
Line: 95
Function: newsdetails
File: /home/sites/43a/5/599366ad77/public_html/index.php
Line: 315
Function: require_once
Opinion Poll
Videos