Kiara Advani, Sidharth Malhotra embrace parenthood for the second time‘Sometimes we get addicted to our own greatness’: Manoj BajpayeeDulquer Salmaan’s ‘Aakasamlo Oka Tara’ gets November 20 release date‘Mirzapur: The Movie’ crosses Rs 100 crore at domestic box office in opening weekendAmitabh Bachchan admits difficulty decoding Gen Z slangWatch: Nagarjuna releases trailer of Allari Naresh-starrer ‘Ramba Oorvasi Menaka’“Tum bahut lambe ho…”: Big B shares struggles of early acting daysNayanthara reveals how Geethu Mohandas convinced her to join ‘Toxic’Sonu Nigam says childhood anger fuelled his passion and shaped his singing careerYash takes out extra time time to pose for selfies with fans before leaving Mumbai airport

Land acquisition stalls Godavari water scheme

Posted February 27th, 2015, 11:37 AM IST

Land acquisition stalls Godavari water scheme

Hyderabad: Though the Krishna Phase-III project is in its trial stage, another water scheme, the Godavari Phase-I, has hit a roadblock due to land acquisition problems.

The project, scheduled to reach trial stage in July, is crucial for Hyderabad as it will feed areas in the city’s fringes. The Godavari Phase-I, which is at its final stage, is facing land acquisition hurdles from the forest department. The project is held up at Mallaram Ring Main II, where land acquisition is essential. The Water Board has brought the matter to the Chief Minister’s notice, said an insider.

“Though other components of this project are moving at a brisk pace, the land acquisition for Ring Main II is yet to be done. However, Water Board MD Jagadeeshwar Rao has coordinated with the Forest department and asked for acquisition of land given the urgency of the project,” said an insider.

Meanwhile M. Satyanarayana, director (Project), Water Board, said, “The land acquisition issue has already been sorted out. We recently held a meeting with agencies involved to expedite the process and complete it by June 30.” The Water Board has already paid Rs 2.7 crore to the Forest department for the 50 acre of land acquired. The money is for plantation of trees in the compensatory afforestation land the Board is providing at Murmur in Karimnagar district.

Godavari Phase-I, a Rs 3,375-crore project, which aims to draw 172 mgd (10 tmc) of water to the city, is progressing at a brisk pace. So far, pipelines have been laid for 138 km out of the total length of 186 km.

Sharing

Photos
Latest

A PHP Error was encountered

Severity: Warning

Message: file_get_contents(http://www.indiaaffiliates.in/ads.php?size=300X250): failed to open stream: Connection refused

Filename: views/newsdetails.php

Line Number: 57

Backtrace:

File: /home/sites/43a/5/599366ad77/public_html/application/views/newsdetails.php
Line: 57
Function: file_get_contents

File: /home/sites/43a/5/599366ad77/public_html/application/controllers/News.php
Line: 135
Function: view

File: /home/sites/43a/5/599366ad77/public_html/application/controllers/News.php
Line: 95
Function: newsdetails

File: /home/sites/43a/5/599366ad77/public_html/index.php
Line: 315
Function: require_once

Opinion Poll
shambo shankara movie
Hit
Average
flop
Advertisement
advertisement
Videos